1.2.2 The Triple Constraint Flashcards

1
Q

Scope/Quality

A

What are the products/services that the
project will produce?

What tasks/activities/work is required to produce these deliverables?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Cost/Resources

A

What money, materials, and personnel are available to deliver the project product/services and to complete the comprehensive work of the project?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  • Time/Schedule
A

What is the amount of time required to complete the all activities of the project?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The job of the project manager is to

A

Ensure that the Triple Constraint Triangle stays in balance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The Triple Constraint Interdependency

A

If one side of the Triple Constraint Triangle changes, so do the other two sides. Take, for example,
a humanitarian NFI (non-food item) distribution project in which the original scope indicated that
10,000 families would be provided with NFI kits (blankets, soaps, etc.). Suddenly, the project
team gets a request to increase the number of families served from 10,000 to 12,000, increasing
the number of kits required by 2,000. This is an increase in the scope of work for the project and
will require that the cost/resources and the time to complete the distribution also increase in
order to successfully implement these activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The project manager needs to

A

understand
1-the relationships
2-trade-offs

that exist between each of
the constraints to effectively manage the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When considering constraints, it may be helpful to

A

think about them
within the context of inflexible
adaptable
may concede.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Inflexible –

A

Indicates that this constraint is
the most critical
must be constrained.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Any change in this constraint results in a negative impact on the project.

A

For example, if you are
implementing a winterization project (providing blankets, winter clothing, etc.) for beneficiaries that needs to take place before the winter season begins, the time is an inflexible constraint.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Another example

A

is an inflexible resource/cost if the project donors’ policies do not allow changes in the
budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If you spend less than originally planned on a specific activity, it doesn’t mean

A

the balance can
be shifted to other activities or transferred to other projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Even though there will be a balance at the end of the project, no adaptation or change is allowed in the budget.

Some donors require that

A

you report the unused funds, which will be deducted from the following project funds transfer or returned
to the donor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Adaptable, May concede

A

Indicates that there is some flexibility within the constraint,

but it should be
optimized as much as possible.

If there is a change needed for the project that affects one of the constraints and that constraint is adaptable, actions can be taken to accommodate the change.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly