12. Types and Classification of Engineering Contract Flashcards
What can contracts for any engineering project be classified as in the first instance?
Contracts Contracts for any particular engineering project can be classified in the first instance as either Main Contracts or as Subcontracts. The essential difference is that a Main Contract is directly between the principal and a Main Contractor, whereas a Subcontract is between a Main Contractor and another contractor, referred to as a Subcontractor.
What are the three most commonly used classification that depend on a particular feature?
A. the method by which the Contractor is selected;
B. the method by which payment for the work under the Contract is evaluated;
C. the method by which responsibility for the technical and administrative aspects of the work is allocated.
What is meant by ‘classification by the method of selection the contractor’ and explain both options?
The principal has two options when selecting the Contractor:
> by a competitive tendering procedure - an agreement is reached between the Principal and a Contractor following a formal competitive tendering procedure in which a number of tenderers are invited to submit bids against a common set of tender enquiry documents (see section 0). This is the most widely used form of engineering contract and is suitable for engineering projects where the nature and extent of the work under the Contract can be clearly identified.
> by direct negotiation with a selected contractor - the principal negotiates directly with a contractor to arrive at a mutually satisfactory agreement to undertake the work. This form of contract is suitable for work of a highly specialised nature or where there are a limited number of contractors experienced in the work required or where the nature of the work cannot be precisely defined. A contract can sometimes be negotiated by a combination of these methods. For example, tenders can be invited from a shortlist of suitable contractors for that part of the work under the contract, which can be precisely defined, and an agreement negotiated for the whole of the work with the contractor who submits the most attractive offer.
What is meant by the term ‘method of payment for work’ and what are the main choices?
The method of payment is of such importance, particularly to the Contractor, that contracts are often classified solely by the method of payment. Payment can be based either on prices (which are submitted by or agreed with the contractor as what he will be paid) or on the actual costs that the contractor incurs.
Main choices are:
• Price Based: Lump Sum or Measure and Value (i.e. Schedule of Rates or Bill of Quantities).
• Cost Based: Cost Reimbursable or Target Cost
What are the main factors that influence the method of payment of work?
:>degree of certainty about the final contract price desired at tender stage.
>flexibility required to cope with design changes likely to be encountered during the contract (can they be systematically and equitably evaluated).
>contractor’s incentive for efficient performance, matched by the promoter’s incentive to provide the contractor with timely information and decisions.
>extent of risk likely to be encountered during the contract and the most cost and time efficient way of allocating it.
What is meant by the payment term ‘lumpsum’?
Also known as a Stipulated Price Contract. The Contractor is paid the amount nominated in the Contract for the work as agreed with the Principal when negotiating the Contract. This amount may of course, be increased or decreased owing to additions to or deletions from the scope of the work under the Contract in accordance with the terms of the agreement. This type of contract is commonly used where the nature and extent of the work can be precisely defined when the Contract is negotiated. Payments may be staged at intervals of time or related to achieved milestones.
What are the implications of the lumpsum payment method?
> complete, final design at tender, so minimum change / variations expected.
high degree of tender competition.
contractor plans efficient use of resources to reduce cost.
no contractual mechanism for price adjustment.
unsuitable when change is expected, therefore rarely used in engineering construction.
price may include high level of financing by contractor and includes risk contingency - likely to be high.
What is meant by the payment term ‘measure and value’?
The Contractor is paid for the work actually done at pre-agreed unit rates. In this type of contract it is important that the items in a Schedule of Rates or the Priced Bill of Quantities cover the whole of the work and that the method of measurement of quantities is clearly defined. Schedule of Rates Contracts are generally used where the nature and extent of the work can be accurately defined but the quantity of work cannot.
What is the definition and purpose of a Bill of Quantities?
Used where items of work are listed with estimated quantities. In UK building and civil engineering, standardised item descriptions and limits to the work included in the item have been drawn up in ‘Standard Methods of Measurement’. Contractors then tender rates against each item. Payment is usually monthly and is derived from measuring quantities of completed work and valuing at rates in the priced Bill of Quantities.
It can be seen therefore that Bills of Quantities have two purposes:
• To provide a basis for the build up of a contractor’s tender estimate and thus to allow tender totals to be compared between bidding contractors; and
• To provide the basis for payment to the contractor once the contract has been awarded.
What is a schedule of rates?
Schedule of Rates Used where prices are tendered against unit – rather than total – quantities, i.e. the overall quantity of work is unknown at tender stage. This provides an increased risk to the contractor.
The implications of this are:
• design may be only partially complete at tender.
• final price invariably different from Tender Total - due to change and delay - which produces claims.
• high degree of tender competition, but uncertainty as to whether the lowest tenderer will yield the lowest final price.
• variations must be provided for with procedure for their evaluation.
• magnitude of contractor financing depends on disparities between costs and revenues.
• price includes risk contingency.
What is meant by the payment term ‘cost reimbursement’ and its main use?
The Contractor is reimbursed the actual costs incurred in carrying out the work under the Contract plus a fee to cover overhead costs and profit. The fee can be one of the following:
• a fixed sum.
• a fixed sum with a profit-sharing or a bonus arrangement.
• a fixed fee with a sliding-scale adjustment.
• a percentage of the costs.
A cost reimbursement contract may also have a guaranteed ceiling price nominated. The main use for a cost reimbursement contract is where the nature, extent or quantity of the work cannot be accurately defined when negotiating the Contract. It requires the contractor’s cost accounts to be open to the promoter.
What is meant by the payment term ‘target cost’?
Based on the setting of a probable (or target) cost for the work. The target cost will subsequently be adjusted for major changes in the work and cost inflation. The contractor’s actual costs are monitored and reimbursed as in a cost-reimbursable contract. Any difference between actual cost and target cost is shared in a specified way between the promoter and the contractor. The sharing is usually set as a percentage ratio e.g. 80:20 with different allocation for savings and excess costs. Both promoter and contractor must be satisfied with the target estimate that should have a reasonable maximum and minimum cost for the work. Usually, as with cost reimbursement, there is a separate Fee for overheads and profit.
What are the incentive provisions for each payment method?
A cost reimbursement contract on a target cost basis automatically includes an incentive for the contractor to reduce costs. For price based contracts such an incentive is already there: if the contractor reduces costs the margin between cost and price is automatically increased. However, any of the payment methods can have some form of additional incentive provisions attached to them. In addition, incentives can relate to criteria other than cost. For example, bonuses may be awarded for early completion (or indeed penalties incurred for late completion).
What is meant by ‘classification by technical and administrative responsibility’?
The implementation of an engineering project involves a number of separate tasks, the responsibility for which must be established clearly from the outset:
• project management and co-ordination;
• engineering design: conceptual, process, detailed (if applicable), documentation
• procurement and supervision;
• construction and supply and/or installation;
• contract administration.
List the 7 classifications under ‘Technical and Administrative Responsibility’
i. separate design and construction;
ii. design and construct contract;
iii. construction supply / installation contract;
iv. management contract;
v. construction management contract;
vi. design and management contract;
vii. turnkey contract.