100 A Flashcards
The MOST correct use of a project network diagram is for _____
Documenting task interdependencies
At a minimum, periodic forecasts must be done at what interval?
As often as specified in the contract documents
The calculated duration for a project is 28.166. The standard deviation is 5.5. What technique would you use to compute the probability of completing a project on a specific day?
Monte Carlo Simulation
The best reason to use multiple calendars is to ___________
More accurately show how the project will be built
During planning you discover that the time needed to complete the project is longer than the time available. What do you do?
Determine options for crashing and/or fast-tracking the project and present management with your recommended option
Free float is the ____________
amount of time an activity can be delayed without impacting the early start of its successor activity
In an activity-on-arrow diagram, the boxes represent:
Task dependencies
Every activity in a schedule, except the first and last activity, should have at least ________
one predecessor and one successor
A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What tool is BEST described here?
Duration compression
An early start constraint dictates __________
The actual start of an activity
Dummy activities are NOT used on which type of network diagram?
PDM
(Precedence Diagram)
Dummy activities ARE used on which 3 types of network diagram?
- CPM
- PERT
- Detailed
Which of the following is NOT required when performing weekly or monthly schedule updates?
Original duration
Which of the following is required when performing weekly or monthly schedule updates?
- Actual finish dates
- Percent complete
- Remaining durations
During the creation of a project plan, you want to find the critical path of the project. Which of the following project management tools would you use to determine the critical path?
Network diagram
T/F
The critical path is frequently defined as the shortest throughout the schedule.
All of the following describe the critical path of a schedule except:
False,
The longest
The critical path of a schedule can be changed by redefining the _______
network logic or activity durations or both
The critical path of a schedule is determined by ________
network logic
The critical path of a schedule is the chain of activities that controls the _____
overall project completion time
The critical path of a schedule can be described as a series of activities that have ________
the least amount of total float
How many types of relationships between activities can be found on a precedence diagram?
4
(FS, SF, SS, FF)
Project delays are best analyzed ________
Contemporaneously with they delay
- Crashing
- Mandatory
- Slack
All of the above relate to ___________ the schedule.
Controlling
Hammock activities in a schedule are included in the ___________ pass calculations
Forward and backwards pass
Hammock activities in a schedule depict a _____ relationship between a sequence of activities in the same path.
Start to Finish
Hammock activities maybe separated by any number of _______
Activities or events in the logic path
Hammock activities do NOT measure the elapsed time between the _______ of a sequence of activities
start and completion
A project manager is involved in the ABC project. Time lines have slipped for project ABC and he feels there could have been a mistake in the initial time estimate of this project. The following are assumptions that he made when doing the initial schedule using the critical path method (CPM). Which one is NOT correct?
The CPM can have no dummies
Which of the following is NOT required while initially planning a project?
Resource identification and leveling
While initially planning a project, include a schedule that identifies ______ on the project
All the tasks required on the project
While initially planning a project, include a schedule that includes the ______ of each task
duration of each task
While initially planning a project, include a schedule with ______ between tasks
Logical relationships between tasks
Project schedules help control all of the following:
- Time
- Cost
- Resources
During the planning phase, Task G was estimated to take five days. Task G is on the critical path. On day two, it became clear that Task G would take 15 days, which will impact the imposed project end date. The project team meets to perform root cause analysis to identify the cause of the variance and to plan schedule recovery with activities performed later in the schedule. What should be the output of this meeting?
Corrective action
The calculation of the latest finish time and latest start time for all incomplete network activities or late time for events in the ADM and PDM scheduling methods is referred to as ______
A backward pass
Which of the following are GENERALLY illustrated better by bar charts than network diagrams?
Progress or status
In an earned value-based system, a schedule performance index of less than one for the project indicates the project is ____________
Behind schedule
You evaluate your critical path and determine the project will be completed two weeks ahead of management’s expected due date. What should you do?
Prepare a list of risks that did NOT occur
An earned value-based project control system can use either of which two budgets as the basis of its calculations?
Labor hours or dollars
While evaluating the Gantt chart, the project manager determines that the project is behind schedule. What should she do?
Evaluate the alternatives with the team
If the optimistic estimate is one, the pessimistic estimate is nine, and the most likely estimate is eight, what is the PERT estimate?
7
In terms of reporting progress to management, a schedule that is organized based on the project’s work breakdown structure is useful because the schedule can be __________
summarized to intermediate levels of detail
The project manager has a project that is three months behind but, surprisingly, markedly under budget. She has decided to try to make up time, but wants to avoid rework. What should she do?
Crash
A total float value less than zero on a schedule activity indicates that the activity is being impacted by ____
an imposed schedule restraint
During schedule development, which of the following would BEST provide the basis for the most likely activity duration estimate?
The schedule for a similar project at the same facility completed 2 years earlier
Total float is defined as the amount of time an activity can be delayed without impacting the _______
overall project completion
What is the duration of a milestone?
Zero (milestones do not have durations)
When creating a baseline project schedule, the ideal outcome is ___________
A zero total float value on the longest path