The MOST correct use of a project network diagram is for _____
Documenting task interdependencies
At a minimum, periodic forecasts must be done at what interval?
As often as specified in the contract documents
The calculated duration for a project is 28.166. The standard deviation is 5.5. What technique would you use to compute the probability of completing a project on a specific day?
Monte Carlo Simulation
The best reason to use multiple calendars is to ___________
More accurately show how the project will be built
During planning you discover that the time needed to complete the project is longer than the time available. What do you do?
Determine options for crashing and/or fast-tracking the project and present management with your recommended option
Free float is the ____________
amount of time an activity can be delayed without impacting the early start of its successor activity
In an activity-on-arrow diagram, the boxes represent:
Task dependencies
Every activity in a schedule, except the first and last activity, should have at least ________
one predecessor and one successor
A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What tool is BEST described here?
Duration compression
An early start constraint dictates __________
The actual start of an activity
Dummy activities are NOT used on which type of network diagram?
PDM
(Precedence Diagram)
Dummy activities ARE used on which 3 types of network diagram?
- CPM
- PERT
- Detailed
Which of the following is NOT required when performing weekly or monthly schedule updates?
Original duration
Which of the following is required when performing weekly or monthly schedule updates?
- Actual finish dates
- Percent complete
- Remaining durations
During the creation of a project plan, you want to find the critical path of the project. Which of the following project management tools would you use to determine the critical path?
Network diagram
T/F
The critical path is frequently defined as the shortest throughout the schedule.
All of the following describe the critical path of a schedule except:
False,
The longest
The critical path of a schedule can be changed by redefining the _______
network logic or activity durations or both
The critical path of a schedule is determined by ________
network logic
The critical path of a schedule is the chain of activities that controls the _____
overall project completion time
The critical path of a schedule can be described as a series of activities that have ________
the least amount of total float
How many types of relationships between activities can be found on a precedence diagram?
4
(FS, SF, SS, FF)
Project delays are best analyzed ________
Contemporaneously with they delay
- Crashing
- Mandatory
- Slack
All of the above relate to ___________ the schedule.
Controlling
Hammock activities in a schedule are included in the ___________ pass calculations
Forward and backwards pass