1-36 Flashcards

Who is or can be in charge.

1
Q

Overall responsibility for compliance with API 653

A

owner

1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Evaluate deterioration on existing shell material

A

Engineer

4.3.1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In a corroded area, find t2 (thinnest area exclusive of pit)

A

Inspector

4.3.2.1.a

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In a corroded area, determine the vertical lines (L)

A

Inspector

4.3.2.1.c

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Perform the Routine In-Service inspection

A

Operator

6.3.1.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Perform the External inspection

A

Owner

6.3.2.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Determine the extent of UT measurements not he shell

A

Owner

6.3.3.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Review the results of CP surveys

A

Owner

6.3.4.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Assure competency of personnel performing CP surveys

A

Owner

6.3.4.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Perform the Internal inspection

A

Inspector

6.4.1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Assure quality and completeness of in-service NDE (robotics) examinations

A

Inspector AND NDE Guru

6.4.1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Determine internal interval based on tank bottom corrosion

A

Owner

6.4.2.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Determine internal interval based on RBI

A

Owner

6.4.2.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Conduct an RBI assessment

A

RBI Guru

6.4.2.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Review and approve RBI assessments

A

Inspector AND Engineer

6.4.2.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Maintain tank records

A

Owner

6.8.1

17
Q

Review inspection findings and recommendations

A

Owner

6.9.3.2

18
Q

Ensure disposition of all recommended repairs and monitoring

A

Owner

6.9.3.2

19
Q

Evaluate and accept NDE examination results

A

Inspector

6.10

20
Q

Authorize all repairs

A

Inspector Or Engineer

9.1.3

21
Q

Authorize all alterations

A

Engineer

9.1.3

22
Q

Designate inspection hold points for repairs, alterations & reconstructions

A

Inspector

9.1.3

23
Q

Provide general authorization for limited routine repairs

A

Inspector

9.1.3

24
Q

Approve all proposed methods of design, materials, WPSs, NDE & testing

A

Inspector Or Engineer

9.1.4

25
Approve all repair, alteration and reconstruction work at hold points
Inspector Or Engineer | 9.1.4
26
Approve all repair, alteration & reconstruction work at completion of work
Inspector Or Engineer | 9.1.4
27
Review and approve the use of non-code specified lap patches on bottom
Engineer | 9.10.1.3
28
Approve lap patch in critical zone if bottom thickness is less than 0.100"
Engineer | 9.10.1.6.b
29
Run the hot tap machine
Qualified Operator | 9.14.5.4
30
Autorize all reconstruction work
Inspector Or Engineer | 10.1.3
31
Review the use of Preheat or Controlled Deposition welding in lieu of PWHT
Engineer | 11.3
32
Concur in writing use of Controlled Dep. welding for malt's of unknown
Engineer And Owner | 11.3
33
Review & approve exempting a hydrotest after a major repair or alteration
Engineer And Owner | 13.3.2.2
34
Authorize FFS evaluation to exempt hydro after major repair or alteration
Owner | 12.3.2.7
35
Perform FFS evaluation to exempt hydro after major repair or alteration
Engineer | 12.3.2.7
36
Perform tank settlement survey
Experienced Person | b.2.1