05. The DSDM Process Flashcards
1
Q
True or False: The focus of Agile Project Manager varies from phase to phase.
A
True
2
Q
True or false: Each phase has defined objectives.
A
True
3
Q
The DSDM process is used to construct _____________ for each project.
A
lifecycle
4
Q
What is the Evolutionary Development phase?
A
Requires the Solution Development Team(s) to apply practices such as Iterative Development, timeboxing, and MoSCoW prioritisation, together with Modelling and Facilitated Workshops.