03.1 Planning for Production Flashcards

1
Q

It means assigning the right amount of resources to each activity at the right time.

A

Resource Allocation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Objective of Resource Allocation

A

Calculate its budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

It is simply trying to maintain uniform daily use of a resource (or resources) for the entire life cycle of the project or for the longest continuous segment of it.

A

Resource Leveling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Also called resource loading

A

Resource allocation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

It is the assignment of the required resources to each activity, in the required amount and timing.

A

Resource allocation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

It is minimizing the fluctuations in day-to-day resource use throughout the project.

A

Resource leveling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

It is usually done by shifting noncritical activities within their available float.

A

Resource leveling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

It attempts to make the daily use of a certain resource as uniform as possible.

A

Resource leveling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

It may be defined as the maximum amount of time an activity can be delayed without delaying the early start of the succeeding activities.

A

Free float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

include labor, equipment, and materials.

A

Resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Leveling resources, starting from project start and going through all project activities, fulfilling their resource requirements and maintaining the total resource usage within the set limits.

A

Forward resource levelling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Some activities have to be delayed until resources are available and the project duration may be greater than planned, causing the finish date to occur later than originally scheduled.

A

Forward resource levelling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Leveling resources, starting from project finish and going (backward) through all project activities, fulfilling their resource requirements and maintaining the total resource usage within the set limits.

A

Backward resource levelling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The project may have a longer duration than originally allowed and project start may have to occur before the scheduled date.

A

Backward resource levelling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

It is defined as the planning and controlling of all necessary efforts to ensure that the correct quality and quantity of materials and equipment are appropriately specified in a timely manner, are obtained at a reasonable cost, and are available when needed (Construction Industry Institute [CII] 1986b)

A

Materials Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly