01 Progress and Quality Control Flashcards
How do you ensure quality control on site?
- Ensure continuous and open communication with Contractor
- Regularly visit site
- Inspect works completed and works in progress of being completed
- Ensure clear instruction and information is given
- Ensure Contractor has allowed adequate time and resources for tasks
How regularly would you inspect a job on site?
At least once a week but frequency will depend on key stages of the programme
What information do you log when visiting site?
- Date, time, weather, number of workers on site
- Review of progress in relation to the programme
- Quality of workmanship (may be necessary to cross-reference with the specification, British Standards, Approved Document 7 etc.)
- Check on materials being used (packaging, labelling etc. if specific products are not identifiable - may need to ask for proof of purchase)
- Ensure works conform to specification and drawings (may need assistance from structural engineer / M&E engineer)
- Take measurements of works where critical (e.g. door opening widths, ceiling heights)
- Health and safety arrangements on site
- Take photographs
How long would you need to keep the records of site visits for?
Records of site visits should be kept for a minimum of 6 or 12 years, depending on how the contract was executed, however negligence claims can be made up to 15 years after work was undertaken, so may need to keep for longer
What do you do if you are not satisfied with the works on site?
- Issue instructions to put the works right
- Instruct Contractor to open works up for inspection
- Exclude unsatisfactory work from interim valuations
- Terminate contract (if the relevant provisions are met, e.g. Contractor not working diligently)
Who bears the cost for works that have to be opened up/uncovered for inspection?
Cost for opening up and making good is borne by the Contractor unless no defect is discovered
What standard procedural methodologies could be used to deliver a construction project?
???
Apart from hitting the completion date, does a contractor have to follow the construction programme?
???
What can you do if a contractor does not finish on time?
Client can claim LADs
What are project deliverables?
Tangible/intangible objects produced as a result of the project that are intended to be delivered to the client (e.g. a part of the site in section completion/partial possession)
What are project milestones?
Specific points along a project timeline that signal how the project is advancing
How would you determine the critical path on a construction programme?
???
Define the term ‘critical path’.
The sequence of critical tasks upon which the overall duration of the project is dependant
Define the term ‘float’.
The ‘spare’ time available in which an activity can be delayed without it impacting the critical path
What is a Gantt Chart?
- A scheduling method that shows activities on the vertical axis and time on the horizontal axis
- Each individual activity is designated a start and completion date which is represented by horizontal bars on the chart
- Used to show the total construction programme and identify the required sequence of work, the critical path and any float on tasks