QUANTITIFCATION & COSTING OF CONSTRUCTION WORKS Flashcards
Why were the New Rules of Measurement introduced?
- SMM7 was designed for the production of bill of quantities for tender purposes.
- NRM was introduced to provide a common and consistent basis for the production of order of cost estimates and cost plans.
What is the structure of the NRM 1?
The key sections of NRM1 are:
* Part 1: General introduction explaining the purpose of the document and how it should be used.
* Part 2: Measurement rules for the production of order of cost estimates.
* Part 3: Measurement rules for the production of elemental cost plans.
* Part 4: Tabulated rules of measurement for elemental cost planning.
* Appendices: With references to the definitions for GIA, functional units, NIA, elemental breakdowns, templates and general information required for cost plan production.
Why should you use the New Rules of Measurement?
- The NRM provides a common and consistent basis for the production of order of cost estimates and cost plans.
- In the event that a QS or firm is pursued for negligence, the use of NRM would provide a means of defence as it represents best practice.
- Colleagues can pick up an estimate and understand the basis of calculations.
What are the NRM 1?
- The RICS New Rules of Measurement 1 is the Order of Cost Estimating and Elemental Cost Planning.
- This provides a structured basis for measuring building works and for the production of Cost Estimates and Cost Plans.
What is meant by the abbreviation GEA?
- Gross External Area.
- This is the area of the building measured externally at each floor level.
- Used in town planning and residential insurance
What is meant by the abbreviation GIA?
- Gross Internal Area.
- This is the area of the building measured to the internal face of the perimeter wall at each floor level.
- The GIA excludes external open sided balconies, fire escapes, canopies, external walls and fuel stores.
- Used for building cost estimation
What is meant by the abbreviation NIA?
- Net Internal Area.
- This is the area of usable space measured to the internal face of the perimeter wall at each floor level.
- The NIA excludes internal structural walls and columns, spaces with headroom less than 1.5m, permanent lift lobbies, toilets, cleaners’ cupboards and plant rooms.
- Used for estate agency and valuation calculations for offices and the like.
Where are all of these abbreviations defined?
- The RICS Code of Measuring Practice (6th Edition) 2015.
(To be superseded by IPMS all buildings)
What is the purpose of the Code of Measuring Practice?
- The Code of Measuring Practice provides precise definitions to permit the accurate and consistent measurement of buildings.
What would you expect the percentage of NIA to GIA to be?
- The percentage would depend on the type of project being undertaken for example whether this was a school, hospital or office.
- In the case of an office building, I would expect the NIA to GIA percentage to be in the region of 70-85%.
- Where 70% is considered as relatively inefficient, a percentage of 85% is extremely efficient.
What do you measure in accordance with?
- Typically the New Rules Measurement, but understand this depends on region/discipline
What is the purpose of a BoQ?
- Provide a contractor with an accurate picture of the scope of works.
- Provide a common and consistent basis for pricing.
- Form basis of tender analysis.
- Provide basis for valuations and change control.
How would you prepare a BoQ?
- I would obtain the complete design information including drawings, spec, schedules etc.
- I would agree with the client the method of measurement to be adopted.
- Prior to commencement of measurement and taking off quantities, I would consider the size of the Project and break the works down into sections and areas for example:-
o Substructure.
o Superstructure.
o External Works. - I would then commence take-off & work in a logical sequence following NRM
- Once measuring is complete I would look to address the general items section & any preambles.
How would you structure a BoQ?
In accordance with an elemental breakdown structure under NRM 2, I would include the following
sections:
* Preliminaries (Main Contract).
* Facilitating Works.
* Substructure.
* Superstructure.
* Internal Finishes.
* Fittings, Furnishings and Equipment.
* Services.
* External Works.
* Provisional Sums.
* Dayworks.
How would you describe the preliminaries section in a Bill of Quantities?
The preliminaries detail items of work that are required to enable the construction but are not associated within the permanent measured works items, such as:-
* Site setup.
* Management & supervision.
* Insurances for the project.
* Task Lighting.
* Protections and temporary barriers.
What information is required to measure preliminaries?
- Contract duration.
- Location.
- Type of project (New Build vs. Refurb).
- The size of the project.
- Temporary works.
- Security.
- Methodology.
- Programme.
- Services.
- Employers accommodation.
- Contractor designed work.
- Sectional completion.
- Insurances / Bonds.
If it was found that a Bill rate was blatantly wrong for example £100 was included as a rate instead of £1, how would this be resolved?
- The works would be valued in accordance with the agreed rate contained within the contract.
- If identified within the tender documents prior to the contract being agreed then the rate could be amended in accordance with the Tendering rules in place, but otherwise both parties would have to stand by the rate.
How do you evaluate a variation which is based on a BQ item which contains an error?
- Assuming the same nature & conditions are applicable, the variation would be based on the BoQ rate within the contract.
- Unless both parties agreed to amend the rate to one that is fair and reasonable.
Who owns the copyright to a BQ?
- The originator owns the copyright.
- This is the QS generally who provides the client permission to use the document for its intended
purpose.
How would you deal with a situation where it was discovered a part of a BQ was missing after the Main Contractor was on site?
- If part of the BQ was missing then I would check to see if it were included as part of the tender
documents & ultimately the contract sum. - If not then the ultimate responsibility would lie with the Employer.
- Providing the works were still required by the Employer they would be treated as a variation to the
contract. - I would request that the contractor price the works & advise the Employer on the level of costs
involved before the instruction is issued.
What would you include within the BoQ where works are to be carried out by Nominated Subcontractor?
A prime cost sum would be incorporated including:
* An allowance for the cost of the Nominated Subcontractors work (based on the quotation).
* An allowance for the contractor to price for attendances such as accommodation, welfare,
storage, handling, materials & cleaning.
* An allowance for a percentage addition for any other charges & profit.
What is a Provisional Sum?
- A Provisional Sum is an allowance included within the BQ for works to be carried out where the extent and design of the work is not yet know meaning the cost cannot be established at the time of agreeing the contract sum.
- This could include works by a nominated subcontractor or supplier, or a statutory authority.