RAC Task Force stands for_______
Rescue Air Cushion Task Force
The RAC is rated for a _____ or _____ fall
10 story or 100ft
The RAC cannot be used above ______ ft
100
A RAC Task Force has a total staffing of ____
7
The dimensions of the RAC are ______
20 x 24
The RAC is first set up in a ________
pre-deployment area – not the target area
For suicidal jumpers, the RAC should be set up ______
Out of sight
The ________ is the safety officer for the overall operation
RAC Task Force CA
The ________ is responsible for securing pri and sec power sources
RAC TF FFS
The primary power source for RAC should be ______
truck or USAR generator
The RAC will inflate in less than _____
60 sec
The RAC tear strength is _______
50 lbs
The _____ absorbs most of the impact
The upper cell
The _________ has twice the energy absorbing capability of the upper cell
Lower cell
The RAC can absorb and dissipate energy in less than ______
1/6 second