Mitchell v News Group
Is the non-compliance trivial/insignificant? If the default was not trivial, why did it occur? Rule was interpreted by the lower courts very harshly
Denton v Davies
Three stage test:
- Identify and assess the seriousness and significance of the failure to comply with the relevant rule, practice direction or court order which engages CPR 3.9(1). If the breach is neither serious nor significant, the relief should be granted
- If the breach is serious or significant, consider why default occurred
- Evaluate all the circumstances of the case to ensure that the court deals with the matter justly, but with particular weight given to the requirements under CPR 3.9
General costs rule
Unsuccessful party pays successful party’s costs (CPR 44.2)
Notice of proposed allocation
Outlines the decision of the court officer as to which track provisionally appears to be most suitable for the claim
DQ
Contains a number of questions to help the court decide which track is most appropriate for the case. In a multi
When must parties file and exchange costs budgets?
7 days before first CMC (CPR 3.13)
What is the consequence for a party who fails to file their costs budget on time?
They are treated as having a budget comprising only the applicable court fees (CPR 3.14)
How is budget defined?
See glossary
When does the relief from sanction under CPR 3.9 not apply?
To an in-time application (when application notice filed prior to expiry of the deadline)
What must the parties do to their budget if there are significant developments in the litigation?
Revise the budget (3E PD 7.6)
When will there be a case management conference?
When a case has been allocated to the multi-track (CPR 29.2)
Where in the CPR does it explain what happens at a CMC?
29 PD 5
What do both parties file and serve after the notice of proposed allocation?
DQ (Form N181) and proposed directions if fast track or multi-track (CPR 26.3(1)(b)(v))
What four documents are required from the parties where there is going to be a CCMC?
- Costs Budget
- Disclosure Report
- Budget discussion report
- Agreed/proposed directions
What is the costs budget form and which CPR applies?