Scrum Master Flashcards
What is the accountability of the Product Owner during Sprint 0?
A. Make the complete project plan to commit date, budget and scope to the stakeholders
B. Make sure enough Product Backlog items are refined to fill the first 3 Sprints
C. Gathering, Eliciting (=herausfinden), and analyzing the requirements that will be inserted into the product Backlog
D. There is no such thing as Sprint 0.
E. Determine the composition of the Development team so they have the capacity to deliver the completed forecast
D. There is no such thing as Sprint 0.
A scrum Master is introducing Scrum to a new Development team. The Development Team has decided that a retrospective is unneccessary. What action should the Scrum Master take?
A. Comply with the deciision of the self-organizing team
B. Begin facilitating productive and useful retrospectives
C. Consult with the Product Owner to see how he/she feels about the situation
D. Call a meeting between the development team and senior management
B. Begin facilitating productive and useful retrospectives
A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which tree techniques would be most helpful in this situation (Select 3)
A. Discuss the absence of the management support with the development teeam
B. Alert maagement to the impediments and their impact
C. tell the product owner that SCRUM isn’t working?
D. arrange a triage meeting with all other project managers
E. Consult with the development Team
F. prioritize the list and work on them in order
B. Alert maagement to the impediments and their impact
E. Consult with the development Team
F. prioritize the list and work on them in order
Who should know the most about the progress toward a business objectiv or a release, and be able to explain the alternatives most clearl? A. Development Team B. Project Manager C. Scrum Master D. Product Owner
D. Product Owner
Which two things are appropriate for a Scrum Master to do if the Development Team doesn’t have the engineering tools and infrastructure to completely finish each selected Product Backlog item? (Select 2)
A. Refocus the current Sprint on establishing the Development Team’s infrastructure instead of delivering an lncrement.
B. Encourage the Product Owner to accept partially done lncrements until the situation improves.
C. Declare the Development Team not ready for Scrum.
D. Have the Development Team establish a Definition of Done that is actually possible to achieve given current
circumstances.
E. Coach the Development Team to improve its skills, tools and infrastructure over time and adjust the Definition of Done accordingly.
D. Have the Development Team establish a Definition of Done that is actually possible to achieve given current
circumstances.
E. Coach the Development Team to improve its skills, tools and infrastructure over time and adjust the Definition of Done accordingly.
A new developer is having continuing conflicts with existing Development Team members and creating a hostile environment. lf necessary, who is responsible for removing the team member? (Select 1)
A. The hiring manager is responsible, because he/she hired the developer.
B. The Product Owner is responsible, because he/she controls
the return on investment (ROl).
C. The Development Team is responsible, and may need help from the Scrum Master.
D. The Scrum Master is responsible, because he/she removes lmpediments.
C. The Development Team is responsible, and may need help from the Scrum Master.
Why should the Product Owner be present at the Daily Scrum? (Select 1)
A. He /She doesn’t need to be there
B. To participate as a Scrum Team member.
C. To hear about impediments in functionality.
D. To represent the stakeholders’ point of view.
A. He /She doesn’t need to be there
A Scrum Master is working with a Development Team that has members in different physical locations. The
Development Team meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before the Daily Scrum. What action should the Scrum Master take? (Select 1)
A. Allow the Development Team to self-manage and determine for itself what to do.
B. Set up the meeting and tell the Development Team that is how it will be done
C. Ask the Development Team members to alternate who is responsible for meeting setup.
D. lnform management and ask them to solve it.
A. Allow the Development Team to self-manage and determine
Who is on the Scrum Team? (Select all that apply) A. Development Team. B. Project Manager. C. Product Owner. D. Scrum Master. E. None ofthe above
A. Development Team.
C. Product Owner.
D. Scrum Master.
An organization has decided to adopt
Scrllm, but management wants to change
the terminology to fit with terminology
already used. What will likely happen if this
is done? (Select 1)
A. Management may feel less anxious (=besorgt).
B. The organization may not understand what has changed
within Scrum and the benefits of Scrum may be lost.
C. Without a new vocabulary as a reminder of the change, very
little change may actually happen.
D. All answers apply.
D. All answers apply.
Cross-functionalteams are optimized to work on a technical layer of system (e.g. GUl, database, middle tier, design contacts). (Select 1) A. True B. False
B. False
- Sprint burndown charts are an efficient
tracking tool because they show: (Select 1)
A. How much effort has gone into a Sprint.
B. How many hours have been worked by each Development
Team member.
C. An estimate of the total work remaining for the Sprint.
D. How many Product Backlog items remain
C. An estimate of the total work remaining for the Sprint.
The maximum length of the Sprint Review (its time box) is: (Select 1) A. L day. B. 2 hours. C. As long as needed. D. 4 hours and longer as needed. E. 4 hours for a monthly Sprint. For shorter Sprints it is usually shorter.
E. 4 hours for a monthly Sprint. For shorter Sprints it is usually shorter.
How often should Development Team membership change? (Select 1)
A. Never, because it reduces productivity.
B. Every Sprint to promote shared learning.
C. As needed, while taking into account a short term reduction in productivity.
D. iust as it would on any development team, with no special allowance (=Anrechnung) for changes in productivity.
C. As needed, while taking into account a short term reduction in productivity.
Which three (3) activities will a Product Owner likely engage in during a Sprint? (Select 3)
A. Update the Sprint burndown chart.
B. Run the Daily Scrum
C. Work with the stakeholders.
D. Provide feedback.
E. Answer questions from the Development Team about items in the current Sprit.
F. Prioritize the Development Team’s tasks.
C. Work with the stakeholders.
D. Provide feedback.
E. Answer questions from the Development Team about items in the current Sprit.
What is the recommended size for a Development Team? (Select 1) A. At least 7 B. 3to9 C. 7 plus or minus 3 D.9
B. 3to9
Which statement best describes the Sprint Review? (Select 1)
A. lt is used to congratulate the Development Team if it did what it committed to doing, or to punish the Development Team if it failed to meet its commitments.
B. lt is a demo at the end of the Sprint for everyone in the organization to provide feedback on the work done.
C. lt is a review of the team’s activities during the Sprint
D. lt is when the Scrum Team and stakeholders inspect the outcome of the Sprint and figure out what to do in the upcoming Sprint
D. lt is when the Scrum Team and stakeholders inspect the outcome of the Sprint and figure out what to do in the upcoming Sprint
lt is mandatory that the product increment be released to production at the end of each Sprint (Select 1)
A True.
B False.
B False.
Which two of the following are true about the Scrum Master role? (Select 2)
A. At the Sprint Review, the Scrum Master identifies what has been “done” and what has not been “done”.
B. The Scrum Master helps those outside team to interact with the Scrum Team.
C. The Scrum Master teaches the Development Team to keep the Scrum meeting to their timebox.
D. The Scrum Master is responsible for updating the Sprint Burndown.
E. The Scrum Master assigns tasks to Development Team members when they need work.
B. The Scrum Master helps those outside team to interact with
the Scrum Team.
C. The Scrum Master teaches the Development Team to keep
What are the benefits of including testing within the Sprint’s development activities? (Select 3)
A. Transparency of the lncrement is increased.
B. The lncrement is closer to being potentially releasable.
C. The lncrement is likely to be more complete.
D. The project manager can more effectively report progress.
A. Transparency of the lncrement is increased.
B. The lncrement is closer to being potentially releasable.
C. The lncrement is likely to be more complete.
The CEO asks the Development Team to add a “very important “ item to the current Sprint. What should the Development Team do? (Select 1)
A. Add the item to the next Sprint.
B. lnform the Product Owner so he/she can work with the CEO.
C. Add the item to the current Sprint and drop an item of equal size.
D. Add the item to the current Sprint without any adjustments.
B. lnform the Product Owner so he/she can work with the CEO.
Who should make sure everyone does his or her tasks for the Sprint? (Select 1) A. The Project Manager. B. The Development Team. C. The Scrum Master. D. The Product Owner. E. Att of the above.
B. The Development Team.
Who owns the Sprint Backlog? (Select 1) A. The Scrum Master. B. The Product Owner. C. The Scrum Team. D. The Development Team.
D. The Development Team.
Which three (3) questions are answered by all Development Team members at the Daily Scrum?
(Select 3)
A. What work did I do yesterday to help the team achieve its goal?
B. What work am I going to do today to help the team achieve its goal?
C. What impediments are in my way or in the way of the team?
D. How is the Sprint proceeding?
E. How many hours did I spend on the project yesterday?
F. Why were you late?
A. What work did I do yesterday to help the team achieve its
goal?
B. What work am I going to do today to help the team achieve
its goal?
C. What impediments are in my way or in the way of the team?
Multiple Scrum Teams working on the same project must have the same start date (Select 1)
A. True.
B. False.
B. False.
Which of the following are true about the length of the Sprint? (Select 2)
A. All Sprints must 1 month or less.
B. Sprint length is determined during Sprint Planning, and should hold the time it will take code the planned features in the upcoming Sprint, but does not include time for testing.
C. Sprint length is determined during Sprint Planning, and should be long enough to make sure the Development Team can deliver what is to be accomplished in the upcoming Sprint.
D. The length of the Sprint should be proportionalto the work that is done in between Sprints.
E. lt is best to have Sprints of consistent length throughout a development effort.
A. All Sprints must 1 month or less.
E. lt is best to have Sprints of consistent length throughout a
development effort.
As Scrum Teams mature (=”ausgereift”) it is expected that the following decision is likely to be taken: (Select 1)
A. Sprint Reviews will no longer be needed.
B. The Sprint Retrospectives will grow to be longer than 4 hours.
C. They will improve their definition of “Done “ to include more stringent criteria.
D. A Scrum Master is no longer needed since they are a mature team now.
E. There is no need for a time-boxed Sprint, since time boxes are only for new Scrum Teams.
C. They will improve their definition of “Done “ to include more stringent criteria.
Every Scrum Team must have a Product Owner and Scrum Master. (Select 1)
A. False
B. True. Each must be tOO% dedicated to the Scrum Team.
C. True. Outcomes are affected by their participation and availability.
C. True. Outcomes are affected by their participation and
availability.
An abnormal termination of Sprint is called when? (Select 1)
A. When Sales has an important opportunity.
B. When the Team feels that the work is too hard.
C. When it is clear at the end of a Sprint that everything won’t be finished.
D. When the Product Owner determines that it makes no sense to finish it.
D. When the Product Owner determines that it makes no sense to finish it.
lf burndown charts are used to visualize progress, what do they track? (Select 1)
A. Work remaining across time
B. lndividual worked productivity
C. Accumulated cost.
D. Accumulated business value delivered to the customer
A. Work remaining across time
Hardening Sprints are dedicated to resolving dependencies and fixing open bugs. Every 3rd or 4th Sprint may be a Hardening Sprint as required. (Select 1)
A. True
B. False
B. False
The Product Owner makes sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders. (Select 1)
A. True.
B. False.
B. False.
When a Development Team is having trouble delivering a working lncrement because they don’t understand a functional requirement, what should they do? (Select 1)
A. Collaborate with the product Owner to determine what is possible and acceptable.
B. Partially complete the functionality, and discuss the remaining work at the Sprint Review.
C. Defer the work to a more appropriate Sprint.
D. Add a specialist to the Development Team.
A. Collaborate with the product Owner to determine what is
Which of these may a Development Team deliver at the end of a Sprint? (Select 1)
A. Failing unit tests, to identify acceptance tests for the next Sprint.
B. A single document, if that is what the Scrum Master asked for.
C. An increment of working software that is “done”.
C. An increment of working software that is “done”.
What is included in the Sprint Backlog? (Select 1)
A. User Stories
B. Use Cases
C. Tasks
D. Tests
E. Any of the above (or others) which are a decomposition of the selected Product Backlog items
E. Any of the above (or others) which are a decomposition of
the selected Product Backlog items
Which does a self-organizing Development Team choose? (Select 1)
A. When to release, based on its progress
B. Product Backlog ordering
C. Sprint length
D. Stakeholders for the Sprint Review
E. How to best accomplish its work
E. How to best accomplish its work
When many Development Teams are working on a single product, what best describes the definition of “done”? (Select 1)
A. Each Development Team defines and used its own. The differences are discussed and reconciles during a hardening Sprint.
B. All Development Teams must have a definition of “Done” that makes their combined work potentially releasable.
C. Each Development Team used its own but must make their definition clear to all other Teams so the differences are known.
D. lt depends.
B. All Development Teams must have a definition of “Done” that makes their combined work potentially releasable.
The Development Team informs the Scrum Master that the lT manager has asked them for a status report during the Sprint. The Scrum Master will: (Select 1)
A. Tell the Development Team to fit the report into their Sprint Backlog.
B. Ask the Product Owner to send unit manager the report.
C. Talk to the lT manager and inform him that progress in Scrum comes from inspecting lncrements at the Sprint Review.
D. Create and deliver the report to the unit manager herself.
E. Tell the Development Team to figure it out themselves.
C. Talk to the lT manager and inform him that progress in Scrum comes from inspecting lncrements at the Sprint Review.
How much of the Sprint Backlog must be defined during the Sprint Planning meeting?
(Select 1)
A. Just enough tasks for the Scrum Master to be confident in the Development Team’s understanding of the Sprint.
B. Just enough to understand design and architectural implication.
C. All of the potential work. The Sprint Planning meeting isn’t over until LOO% of the work is identified and estimated.
D. Enough so the Development Team can create its best forecast
of what it can do, and to start the first severaldays of the Sprint.
D. Enough so the Development Team can create its best forecast of what it can do, and to start the first severaldays of the
Sprint.
Which technique is the LEAST productive way for the Scrum Master to ensure that the Development Team communicates effectively with the Product Owner? (Select 1)
A. Monitor communications between them.
B. Teach the Product Owner about the technologies employed during the Sprints
C. Act as a go-between for them.
D. Teach the Team to talk in terms of business needs and objectives.
C. Act as a go-between for them.
lf burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate? (Select 1)
A. When the project will be over if the product Owner removes work that is equal in effort to any new work that is added.
B. When all work will be completed so the Scrum Team can be released for the cost spent on the project.
C. The evolution of the cost spent on the project will likely be completed if nothing changes on the Product Backlog or the Development Team.
D. When the work remaining will likely be completed if nothing changes on the Product Backlog or the Development Team
D. When the work remaining will likely be completed if nothing changes on the Product Backlog or the Development Team
During the Daily Scrum, the Scrum Master’s role is to: (Select 1)
A. Make sure that all 3 questions have been answered.
B. Teach the DevelopmentTeam to keep the Daily Scrum within the 15 minute timebox.
C. Manage the meeting in a way that each team member has a chance to speak.
D. Lead the discussions of the Development Team.
E. All of the above.
B. Teach the DevelopmentTeam to keep the Daily Scrum within
the 15 minute timebox.
Scrum is a methodology that tells in detail how to build software incrementally.
(Select 1)
A. True
B. False
B. False
Which statement best describes a Product Owner’s responsibility? (Select 1)
A. Keeping stakeholders at bay (=Stakeholder fernhalten).
B. Managing the project and ensuring that the work meets the commitments to the stakeholders.
C. Directing the Development Team.
D. Optimizing the value of the work the Development Team does.
D. Optimizing the value of the work the Development Team does.
Which of the following might the Scrum Team discuss during a Sprint Retrospective?
(Select 1)
A. lts Definition of “done”.
B. The way the Scrum Team does Sprint Planning.
C. Methods of communication.
D. Skills needed to improve the Development Team’s ability to deliver.
E. All of the above.
E. All of the above.
Who is responsible for tracking the remaining work of the Sprint? (Select 1) A. The Scrum Master B. The Development Team C. The Project Manager D. The Product Owner E. The Development Team in consultation with the Product Owner
B. The Development Team
Which two things does the Development Team NOT do during the first Sprint? (Select 2)
A. Develop a plan for the rest of the project.
B. Develop and deliver at least one piece of functionality.
C. Deliver an Increment of potentially releasable functionality.
D. Nail down the complete architecture and infrastructure.
A. Develop a plan for the rest of the project.
D. Nail down the complete architecture and infrastructure.
When multiple teams are working together on the same product, each team should maintain a separate Product Backlog.
(Select 1)
A. True
B. False
B. False
While under development, the environment in which a product will be used changes and emerges. What is the effect on the Product Backlog? (Select 1)
A. There is no effect, because it has to stay the same until the end of the project.
B. lt is archived and a new Product Backlog is created to take its place.
C. lt evolves to reflect what the product needs to be most valuable.
D. The requirements specification document, describing the Product Backlog items, must be updated to ensure stability.
C. lt evolves to reflect what the product needs to be most valuable.
Choose three responsibilities of selforganizing a Development Team. (Select 3)
A. Report daily progress to stakeholders.
B. Reorder the Product Backlog.
C. Do the work planned in the Sprint Backlog.
D. Pull Product Backlog items for the Sprint.
E. Set the time for the Daily Scrum.
C. Do the work planned in the Sprint Backlog.
D. Pull Product Backlog items for the Sprint.
E. Set the time for the Daily Scrum.
When should a Sprint Goal be created?
(Select 1)
A. lt should have been created in the previous Sprint during
Prod uct Backlog refinement.
B. During Sprint Planning.
C. A Sprint Goal is not mandatory in Scrum
D. At any time established before Sprint Planning in order to
begin planning.
B. During Sprint Planning.
Which of the following best describes an increment of working software? (Select 1)
A. Additional features in a useable state that complement those delivered in previous iterations.
B. A new user interface design for functionality delivered in previous iterations.
C. A decomposition of all Product Backlog items into tasks for future Sprint Backlog lists.
D. UML diagrams that describe how to deliver functionality in future iterations.
E. An automated test suite to verify functionality delivered in previous iterations.
A. Additional features in a useable state that complement those delivered in previous iterations.
Who is required to attend the Daily Scrum? (Select 1)
A. The Development Team
B. The Development Team and Product Owner
C. The Scrum Team
D. The Scrum Master and Product Owner
E. The Development Team and Scrum Master
A. The Development Team
When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint? (Select 1)
A. No, that is far too hard and must be done in a hardening Sprint.
B. No, each Scrum Team stands alone.
C. Yes, but only for Scrum Teams whose work has dependencies.
D. Yes, otherwise the Product Owners (stakeholders) may not be able to accurately inspect what is done
D. Yes, otherwise the Product Owners (stakeholders) may not be able to accurately inspect what is done
What does it mean for a Development Team to be cross-functional? (Select 1)
A. The Development Team includes not only developers but also business analysts, architects, developers and tester.
B. Developers on the Development Team work closely with business analysts, architects developers and testers who are not on the team.
C. The Development Team includes cross-skilled individuals who are able to contribute to do what is necessary to deliver an increment of software.
D. The Development Team is a virtualteam drawing from separate teams of business analysts, architects, developers and testers.
C. The Development Team includes cross-skilled individuals who are able to contribute to do what is necessary to deliver an increment of software
The Product Owner remains distant. He/she has handed over the required Product Backlog for the Sprint but is not collaborating with the Development Team during the Sprint. What are valuable actions for a Scrum Master? (Select 2)
A. lnform the Product Owner’s functional manager.
B. Nominate a proxy Product Owner.
C. Coach the Product Owner in the values of Scrum and incremental delivery.
D. Stop the Sprint, send the Product Owner to a course and restart.
E. Bring up the problem in the Sprint Retrospective.
C. Coach the Product Owner in the values of Scrum and incremental delivery.
E. Bring up the problem in the Sprint Retrospective.