SAFe 5.1 RTE Lesson 6 Flashcards
What are the three main activities of Inspect & Adapt?
- PI System Demo,
- Quantitative and Qualitative Measurement,
- Problem-Solving Workshop
During the IA, the RTE reviews each Team’s performance. (True or False)
False. The RTE reviews ART performance.
The PI Performance Report artifact is used to do what?
Assess business value achieved for each PI Objective.
What technique is used to identify problems afflicting the ART?
Ishikawa (Fishbone) Diagram
What method is used to identify the likely root cause of a problem afflicting the ART?
5-Whys
What method is used to ascertain the most impacting problem afflicting the ART?
Pareto Analysis
What is another name for the Pareto Analysis?
80/20 Rule
What type of visualization does the Pareto Analysis use?
Histogram
What can an RTE do to understand ART health?
Conduct an assessment
How many data points must you have to detect a trend?
3
Why should assessments be conducted on a cadence?
To reveal the degree of change and detect any trends.
What type of ‘thinking’ should an RTE use when assessing the ART?
System Thinking
What is a powerful technique the RTE can use to enable System Thinking assessment of the ART?
Value Stream Mapping
Value Stream Mapping is a scaled version of what Six Sigma practice?
Process Mapping
What are the four core measurements in Value Stream Mapping?
- Processing Time,
- Lead Time,
- Activity Ratio,
- %Complete and Accurate