Resource Scheduling and Optimisation Flashcards

1
Q

The critical path on a project network is:

A the shorts path in duration through the network.

B the path with the most float.

C the path with the most activities on it.

D the longest path in duration through the network.

A

D the longest path in duration through the network.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The critical path in the network diagram shown below is:

A 5 - B 5 - D 5 - F 5
\ /
C 4 - E 4

A ACEF

B ABDF

C ACDF

D ABEF

A

B ABDF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In the above network diagram, which of the activities have total float:

A C and E

B B and D

C A only

D E only

A

A C and E

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The diagram below shows the relationship between task A and task B.

Task A ______Task B

According to this diagram the dependency shown is an example of:

A Finish to start

B Finish to finish

C Start to finish

D Start to start

A

B Finish to finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which of the following best describes the concept of total float?

A The value of the earliest finish of an activity subtracted from the latest finish of the previous activity.

B The value of the latest finish of an activity subtracted from the earliest start of the same activity.

C The amount an activity can slip without affecting the overall duration of the project.

D The amount an activity can slip without affecting the start of the next activity.

A

C The amount an activity can slip without affecting the overall duration of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

In a situation where time becomes more important than cost, the project manager should first attempt to:

A remove resources from critical tasks.

B perform time limited scheduling (smoothing).

C redefine the critical path.

D perform resource limited smoothing (levelling).

A

B perform time limited scheduling (smoothing).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

To maintain the scheduled duration when resources are limited, resource levelling should first attempt to:

A not exceed pre-determined end date.

B schedule activities within the limits of their floats.

C extend the activity duration.

D minimise the use of overtime.

A

B schedule activities within the limits of their floats.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The Gantt chart below shows the scheduling of seven tasks (A-G) and their daily allocation of resources over a 9 day period. Activities B and F have total float to the extent as indicated by the dotted line.

A 2 2 2

B 3 3

C 1 1

D 2 2 2

E 2 2

F 3——-

G 2

   1 2 3 4 5 6 7 8 9

Which of the possible actions would be considered the best application of resource smoothing?

A Double the amount of resources applied to activity B, reducing its duration to 1 day.

B Delay activity F to start on day 5 and finish on day 7, reducing to 1 resource per day.

C Extend the overall schedule duration by 3 days and start the project on day 3.

D Double the amount of resources applied to activity E reducing its duration to day 1.

A

B Delay activity F to start on day 5 and finish on day 7, reducing to 1 resource per day.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A 2 2 2

B 3 3

C 1 1

D 2 2 2

E 2 2

F 3——-

G 2

   1 2 3 4 5 6 7 8 9

If the total number of resources available is limited to 6 per day, what would be the most efficient way to deal with this constraint?

A increase the project budget to acquire additional resources.

B Extend the overall project duration by 3 days.

C Move activity B and F to the extent of their float.

D Move activity F only to start on day 5.

A

D Move activity F only to start on day 5.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A 2 2 2

B 3 3

C 1 1

D 2 2 2

E 2 2

F 3——-

G 2

   1 2 3 4 5 6 7 8 9

If resource levelling was being considered to be applied to the schedule, which activities should be initially considered for this technique?

A All activities would be considered.

B Activities B and F would be initially considered.

C Activities A, C, D, E and G would be initially considered.

D There is not enough information provided to make such a decision.

A

B Activities B and F would be initially considered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Procurement could be described as:

A an outline of the deliverables required by the project.

B a process by which the resources required by the project are acquired.

C an outline of the resources required for the project.

D a definition of who should be the best supplier of goods for the project.

A

B a process by which the resources required by the project are acquired.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Preparation of contracts, selection and acquisition of suppliers and management of the contracts would be items recorded in the:

A Responsibility matrix.

B Work breakdown structure.

C Business case.

D Procurement strategy.

A

D Procurement strategy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

One key principle a project manager should follow when carrying out procurement is to:

A ensure the same suppliers are used in each project to maintain consistency.

B always use the supplier who will offer the lowest price.

C always bring in specialist help for support.

D always use an objective process when selecting suppliers.

A

D always use an objective process when selecting suppliers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which of the following would best describe a contract?

A An agreement made between two or more parties that creates legally binding obligations between them.

B An invitation for a supplier to tend at the lowest price.

C A stage or work package carried out by a chosen supplier.

D An accepted completed work package.

A

A An agreement made between two or more parties that creates legally binding obligations between them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When acquiring goods or services for the project what might be the most important question for the project manager to raise with the sponsor with regard to contract?

A How many suppliers from the market might be willing to submit a tender response.

B If the previous supplier to the project can also be used for the project currently being planned.

C How much risk to retain in the project and how much to share with suppliers in the supply chain?

D How much previous experience does the organisation have with the suppliers that are currently being considered?

A

C How much risk to retain in the project and how much to share with suppliers in the supply chain?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly