Project Management Flashcards

1
Q

Project definition

A

a project is a unique effort with a defined beginning and end, a specific deliverable, and specified resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

program management

A

group of related projects managed together as a unit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

portfolio management

A

a collection of projects and programs managed together (bigger branch)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

3 constraints need to be managed within a project

A
  1. schedule
  2. resources
  3. scope (overal impact of the project)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Project Structure

A
  1. Define and Organise the Project
  2. Plan the Project
  3. Manage Project Progress
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

POS

A

project objective statement
30-40 words
clear statement of owner, scope, schedule, and resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Priority Matrix

A

schedule scope resources

least flexible

moderate

most

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

WBS

A

Work Breakdown Structure

hierarchy of all work to be accomplished on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

maximum and minimum duration of tasks

A

3-5 days minimum

2 weeks maximum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Project time management

A
  • what
  • which order
  • who and how long
  • when
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

early finish

A

early finish = early start + duration - 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

late start

A

late start = late finish - duration + 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

slack

A

slack = late finish - early finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly