PM SITE 3 Flashcards
A project has activities on the critical path that must be completed before other activities can start.
Task A is dependent on Task C before Task D can be completed.
Task A requires task B to start.
Task B takes twice as long to complete as Task C.
Which of the following is the appropriate ordering of the critical path?
A. B, A, D
B. C, B, D, A
C. D, A, C
D. B, C, A, D
D. B, C, A, D
Which of the following job roles is primarily tasked with communicating the project timeline changes?
A. Project scheduler
B. Project manager
C. Project sponsor
D. Project coordinator
B. Project manager
A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000.
Which of the following steps should the project manager perform NEXT?
A. Wait until the change requests are approved by the CCB.
B. Approve the changes because the additional functionality is required to complete the process.
C. Speak with the project sponsor and provide a detailed analysis of the changes and impacts to the project budget.
D. Schedule the changes as part of the second phase of the project when additional funding will be available and work can be completed.
A. Wait until the change requests are approved by the CCB.
The chairperson of the board is visiting from another country and wishes to meet the project team members. The next project team meeting will be held next week, but the chairperson is leaving before the meeting. Which of the following actions should the project manager take?
A. Schedule a conference call for the team meeting and invite the chairperson.
B. Arrange an impromptu team meeting with the chairperson.
C. Email the chairperson the meeting minutes from the scheduled meeting
D. Invite the chairperson to the next project team meeting
B. Arrange an impromptu team meeting with the chairperson.
Which of the following are characteristics of a project? (Choose two.)
A. A project is a temporary endeavor.
B. A project provides a unique product, service, or result.
C. A project is an ongoing endeavor.
D. A project involves scheduled maintenance.
E. A project includes life-cycle cost management.
A. A project is a temporary endeavor.
B. A project provides a unique product, service, or result.
A project team has purchased computers with warranties extending throughout the entire project. Which of the following represents the risk strategy utilized?
A. Transfer
B. Share
C. Mitigate
D. Avoid
C. Mitigate
Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?
A. SCRUM retrospective meeting
B. Sprint planning meeting
C. Daily standup meeting
D. Review meeting
B. Sprint planning meeting
The project manager of a global project constantly receives complaints from individuals at another location that some team members are not available after lunch on Fridays. This is acceptable to the project manager. Which of the following factors is the MOST likely cause for this scenario?
A. Personal preference
B. Intra-organizational differences
C. Culture
D. Time zone
D. Time zone
A project manager is providing the lessons learned for a project that ran over budget and produced poor quality deliverables. Which of the following should the project manager include as part of the lessons learned?
A. Risk register
B. Post-mortem analysis
C. Issue log
D. Procurement report
B. Post-mortem analysis
A company decides to give a large section of its development project to another firm to manage and complete because that firm has the appropriately skilled resources to execute the work. This approach is referred to as:
A. Resource leveling
B. Staff Augmentation
C. Work relocation
D. Outsourcing
D. Outsourcing
An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast-tracked tasks that require additional hours. Which of the following documents did the project manager fail to reference?
A. MOU
B. MOA
C. SOW
D. SLA
B. MOA
Which of the following roles has approval authority for project funding?
A. Champion
B. Chief Financial Officer (CFO)
C. Project Management Office (PMO)
D. Sponsor
D. Sponsor
A software upgrade project has been postponed because it may impact a critical business system. Which of the following strategies has been applied?
A. Accept risk
B. Mitigate risk
C. Avoid risk
D. Exploit risk
C. Avoid risk
The project team is distributed throughout a single country. The scrum master has decided to hold remote “stand-ups” on a daily basis. Which of the following would be the MOST effective means to do this?
A. Instant messaging
B. Video conference
C. Phone call
D. Collaboration website
B. Video conference
Which of the following is an example of a project?
A. Purchasing pedometers from local retail stores for employees
B. Implementing a health awareness program at an organization
C. Conducting semi-annual blood drives at an organization
D. Presenting a scripted workshop at an organizations three locations
B. Implementing a health awareness program at an organization
A project is about to begin the execution phase. The SOW and project plan have been approved, and the project team has been formed. Which of the following types of meetings should happen NEXT?
A. Update
B. Scheduling
C. Kickoff
D. Review
B. Scheduling
A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during project planning?
A. Issue log and process diagram
B. Resource analysis and Gantt chart
C. Stakeholder analysis and communication plan
D. Scatter chart and scope analysis
B. Resource analysis and Gantt chart
A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float
for the two tasks. Which of the following represents the number of days the project schedule will be delayed?
A. Zero
B. One
C. Two
D. Three
D. Three
A software development project is struggling with a certain technology that is unknown to the project team. A project manager has received a third-party proposal to transfer the risk.
Which of the following should the project manager do NEXT?
A. RF1 B. RFP C. RFQ D. Change request E. Request for bid
E. Request for bid
A team member learns that an assigned task is not due until the very end of the project. Moreover, the team member is not aware of any predecessor tasks dependent on completing the assigned task. Which of the following does the project manager use to decide if the team member can start the task later or earlier?
A. Review the PERT chart and evaluate if the task is a critical dependency.
B. Review the PERT chart and evaluate if the task is a discretionary dependency.
C. Review the PERT chart and evaluate if the task is a real dependency.
D. Review the PERT chart and evaluate if the task is an external dependency.
B. Review the PERT chart and evaluate if the task is a discretionary dependency.