Multiple choice Flashcards
1) A series of activities to create a unique product or service by a specific date is best described as
which one of the following?
A. A program
B. An operation
C. A project
D. A subproject
C. A project
2) Which of the following is likely to be part of an operation?
A. Providing electricity to a community
B. Designing an electrical grid for a new community
C. Building a new dam as a source for electricity
D. Informing the public about changes at the electrical company
A. Providing electricity to a community
3) Of the following, which one is the best example of progressive elaboration?
A. It is the process of decomposing the work into small, manageable tasks.
B. It is the process of taking a project from concept to completion.
C. It is the process of taking a project from concept to detailed project plan.
D. It is the process of identifying the business needs of a potential project.
C.It is the process of taking a project from concept to detailed project plan.
4) Of the following, which one is not a typical activity of a project manager?
A. Controlling the project work
B. Planning the project schedule
C. Milestone completion
D. Planning
C. Milestone completion
5) In what process is the project manager selected to manage a project?
A. Initiation
B. Planning
C. Controlling
D. Design
A. Initiation
6) What is the project scope?
A. It is the design of experiments used to complete the project work
B. It is the combination of the cost and the schedule required to complete the project work
C. The description of the required work, and only the required work, to complete the project
D. The resources required completing the work
C. The description of the required work, and only the required work, to complete the project
7) The closing process is also known as which of the following?
A. Project completion
B. Project postmortem
C. Project wake
D. Project parity
B. Project postmortem
- Which of the following is not a project management process?
A. Initiating
C. Controlling
B. Planning
D. Designing
D. Designing
- You are the project manager of the Speaker Design Project. Your project sponsor wants to know
why you believe the planning process will last throughout the project. Of the following, which is the
best answer?
A. You are not very familiar with speakers and will have to revisit the planning process often.
B. The design of a new product requires planning throughout the closing process.
C. The design of any project should allow the project manager and the project team to revisit the
planning phase as needed.
D. All processes within a project are iterative.
C. The design of any project should allow the project manager and the project team to revisit the
planning phase as needed.
- Of the following, which one is not part of Project Integration Management?
A. The creation of the project plan
B. The interaction between project teams
C. The execution of the project plan
D. The documentation of changes to the project plan
B. The interaction between project teams
- The project life cycle is comprised of which of the following?
A. Phases
B. Milestones
C. Estimates
D. Activities
A. Phases
- Marcy, the project manager for the ERP Project, is about to complete the Project Phase Review. The
completion of a project phase is also known as which of the following?
A. Lessons learned
B. Kill points
C. Earned Value Management
D. Conditional advancement
B. Kill points
- Which of the following is not a key stakeholder in a project that creates a service internal to an
organization?
A. Project manager
B. External customers
C. Project vendors
D. Project team members
B. External Customers
- Of the following management skills, which will a project manager use most?
A. Leading
B. Communication
C. Influencing the organization
D. Negotiations
B. Communication
- Managing is best described as which one of the following?
A. Establishing direction
B. Functional controls over the project team and stakeholders
C. Consistently producing key results expected by stakeholders
D. Motivating and inspiring the project team to produce results that are expected by stakeholders
C. Consistently producing key results expected by stakeholders
- Ron, the project manager, expects formal communications for change requests. Of the following,
which is most likely not an example of formal communication?
A. Reports
B. Oral presentations
C. E-mail
D. Team meetings
C. E-mail