Mock Exam Qu’s Flashcards

1
Q

Explain 2 difference between single and multiple suppliers in a project

A

Procurement and management is simple with single and more complex with multiple

Control and risk over the supply chain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Explain 3 reasons why a project should use a robust supplier selection process

A

To ensure make or buy in has been considered

Ensure best supplier is identified

Protect project from unnecessary risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Explain 3 stages of supplier selection

A

Pre qualification
Tendering/bidding
Evaluating bids
Negotiation/Contract award

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Explain 3 differences between perm and temp types of org structures

A

Perm is funded through annual budget, temp funded through business case

Perm uses outputs to generate benefits, temp generates the benefits

Perm team is established and well formed, temp team are unfamiliar and new