Explain 2 difference between single and multiple suppliers in a project
Procurement and management is simple with single and more complex with multiple
Control and risk over the supply chain
Explain 3 reasons why a project should use a robust supplier selection process
To ensure make or buy in has been considered
Ensure best supplier is identified
Protect project from unnecessary risk
Explain 3 stages of supplier selection
Pre qualification
Tendering/bidding
Evaluating bids
Negotiation/Contract award
Explain 3 differences between perm and temp types of org structures
Perm is funded through annual budget, temp funded through business case
Perm uses outputs to generate benefits, temp generates the benefits
Perm team is established and well formed, temp team are unfamiliar and new