Equations Flashcards

1
Q

Present Value

A

PV = FV/(1+i)^t

FV = Future value
i= interest rate
t= time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PERT

A

Program Evaluation and Review Technique

PERT = (P+4ML+O)/6 P=pessimistic, ML= Most Likely, O=Optimistic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

One Standard Deviation

A

1 Standard Deviation = |(P-O)/6|

1 Standard Deviation = |((UCL-LCL)/6)|

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Variance

A

Variance = (SD)^2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV

A

Current value (CV)=EV-AC EV=earned value, AC=actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost Performance Index (CPI)

A

CPI=EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Schedule Variance (SV)

A

SV = EV-PV EV=earned value, PV = planned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Schedule Performance Index (SPI)

A

SPI= EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate at Completion (EAC): Assume we will continue to spend at the same rate

A

EAC=BAC/CPI BAC=budget at completion, CPI=cost performance index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate to Complete (ETC): Assume we will continue to spend at the same rate

A

ETC=EAC-AC EAC=estimate at completion, AC=actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Variance at Completion (VAC)

A

VAC=BAC-EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI: using BAC

A

TCPI=(BAC-EV)/(BAC-AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

TCPI: using EAC

A

TCPI=(BAC-EV)/(EAC-AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Number of communications channels

A

of channels = (n(n-1))/2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Point of Total Assumption (PTA)

A

PTA= target cost+((ceiling price-target price)/buyer’s share ratio)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Estimate at Completion (EAC): Assume the remaining work will be accomplished at the original planned rate

A

EAC=AC+(BAC-EV)

17
Q

Estimate at Completion (EAC): Assume both CPI and SPI will influence remaining work

A

EAC=AC+((BAC-EV)/(SPI*CPI))

18
Q

Estimate at Completion (EAC): Assume plan and current spending do not represent future

A

EAC=AC+bottom-up ETC

19
Q

Estimate to Complete (ETC): Assume need to reestimate

A

ETC=Bottom-up ETC