Equations Flashcards
Present Value
PV = FV/(1+i)^t
FV = Future value i= interest rate t= time
PERT
Program Evaluation and Review Technique
PERT = (P+4ML+O)/6 P=pessimistic, ML= Most Likely, O=Optimistic
One Standard Deviation
1 Standard Deviation = |(P-O)/6|
1 Standard Deviation = |((UCL-LCL)/6)|
Variance
Variance = (SD)^2
CV
Current value (CV)=EV-AC EV=earned value, AC=actual cost
Cost Performance Index (CPI)
CPI=EV/AC
Schedule Variance (SV)
SV = EV-PV EV=earned value, PV = planned value
Schedule Performance Index (SPI)
SPI= EV/PV
Estimate at Completion (EAC): Assume we will continue to spend at the same rate
EAC=BAC/CPI BAC=budget at completion, CPI=cost performance index
Estimate to Complete (ETC): Assume we will continue to spend at the same rate
ETC=EAC-AC EAC=estimate at completion, AC=actual cost
Variance at Completion (VAC)
VAC=BAC-EAC
TCPI: using BAC
TCPI=(BAC-EV)/(BAC-AC)
TCPI: using EAC
TCPI=(BAC-EV)/(EAC-AC)
Number of communications channels
of channels = (n(n-1))/2
Point of Total Assumption (PTA)
PTA= target cost+((ceiling price-target price)/buyer’s share ratio)