Earned Value Formulas Flashcards
Budgeted at Completion
BAC
How much will it cost?
Planned Value
PV
What is our planned spending?
Earned Value
EV
What has been earned to date?
Actual Cost
AC
What has been spent up to date?
Cost Variance
CV
What is the difference from the planned costs?
CV = EV - AC
If CV is negative, the task is over budget
If CV is zero, the project is on budget
If CV is positive, the project is under budget
Schedule Variance
SV
What is the difference from the planned schedule?
SV = EV - PV
Cost Performance Index
CPI
What is the value for money?
CPI = EV / AC
If CPI < 1, the task is over budget
If CPI = 1, the task is on budget
If CPI > 1, the task is under budget
Schedule Performance Index
SPI
What is the current progress vs the planned schedule?
SPI = EV / PV
If SPI < 1, the task is behind schedule
If SPI = 1, the task is on schedule
If SPI > 1, the task is ahead of schedule
Estimate at Completion
EAC
What will be the final costs according to the current schedule and costs?
The reason for the variance is likely to continue.
EAC = BAC / CPI
The reason for the variance is not likely to continue. The project performance is expected to return to planned levels.
EAC = AC + (BAC – EV)
When you feel the project’s future cost performance is likely to be impacted by the past schedule performance as well as cost, you can use a hybrid.
EAC = AC + [(BAC – EV) / (SPI x CPI)]
When you need to change the estimate because the initial assumptions were wrong.
EAC = AC + ETC
Estimate to Completion
ETC
How much will it cost to complete from current point in time?
ETC = BAC / CPI
Variance at Completion
VAC
What is the difference between the original budget and what will be spent to complete?
VAC = BAC - EAC
If VAC is negative, you need that much more money to complete the project.
If VAC is positive, you will finish the project with that much of a surplus
CPI Cumulative
CPIC
What are the peformance efficiency factors at performance each review?
CPIC = Σ EV / Σ AC
To Complete Performance Index
TCPIC or TCPIs
What is the performance needed to meet the cost/schedule goals?
For Original Budget:
TCPIC = (BAC - EV) / (BAC – AC)
For Current Forecast
TCPIC = (EAC - EV) / (EAC – AC)