Cost Flashcards
What is ROM - Rough Order of Magnitude Calculation
a general estimate of a project’s level of effort and cost
– 25 percent to + 75 percent.
What is the PERT Estimate Calc?
0+4(m)+P then divide by 6
Analogous Estimating
Using previous projects to estimate this one
Bottom Up Estimating
examining the work at the most granular level of detail, compiling all this information, and then coming up with an overall budget and timeline for a project that can be delegated to team members.
Difference between Parametric and Analogous Estimating
Analogous estimating is basically comparing one project to another and is used when there is limited information available.
Parametric estimating is based on unit rates per activity. It is much more accurate when there is data available
T/F The cost management plan include procedures to account for Fluctuation in currency exchange
True
What is the three point estimate calculation method
(P + M + 0) / 3
Earned Value
amount of work that we have actually done/completed at this point in time is the Earned Value
Planned Value
The amount of work that we should have done
T/F Cost Base line is a results of Determine Budget
True
What is EEF
Enterprise Environmental Factor - represents a factor that the project team has very little control over
What category will recall costs fall under?
Cost of quality
If you are looking at reserves for costs incurred for risks outside of the risk register, where would those come from?
Management reserves, and they are not included in the cost baseline
If the question asks for ‘input’ what does this refer to?
An artifact, or document
What is estimate to complete?
ETC is how much money/time we need to complete the remaining work of the project.