Cost Flashcards

1
Q

What is ROM - Rough Order of Magnitude Calculation

A

a general estimate of a project’s level of effort and cost

– 25 percent to + 75 percent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the PERT Estimate Calc?

A

0+4(m)+P then divide by 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Analogous Estimating

A

Using previous projects to estimate this one

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Bottom Up Estimating

A

examining the work at the most granular level of detail, compiling all this information, and then coming up with an overall budget and timeline for a project that can be delegated to team members.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Difference between Parametric and Analogous Estimating

A

Analogous estimating is basically comparing one project to another and is used when there is limited information available.

Parametric estimating is based on unit rates per activity. It is much more accurate when there is data available

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

T/F The cost management plan include procedures to account for Fluctuation in currency exchange

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the three point estimate calculation method

A

(P + M + 0) / 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Earned Value

A

amount of work that we have actually done/completed at this point in time is the Earned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Planned Value

A

The amount of work that we should have done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

T/F Cost Base line is a results of Determine Budget

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is EEF

A

Enterprise Environmental Factor - represents a factor that the project team has very little control over

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What category will recall costs fall under?

A

Cost of quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If you are looking at reserves for costs incurred for risks outside of the risk register, where would those come from?

A

Management reserves, and they are not included in the cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

If the question asks for ‘input’ what does this refer to?

A

An artifact, or document

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is estimate to complete?

A

ETC is how much money/time we need to complete the remaining work of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How do you calculate CPI?

A

CPI = (percentage towards the project completion X Budget at completion)/ How much you have spent

17
Q

Which estimate is used when quickly getting a response?

A

Parametric

18
Q

Cost baseline is an output of what?

A

Determine Budget

19
Q

How do you calculate Earned Value?

A

percent towards completion x Budget at Completion

20
Q

What are two likely baseline inputs to Cost Control

A

Performance Measurement Baseline and Cost Baseline

21
Q

The Cost Management Plan will include what?

A

instructions on how the team should be reporting out on performance measurement on activities

22
Q

If you are estimating in a predictive lifecycle approach, what tecnique are you using?

A

Analogous