Contract Practice Flashcards
Memorise
Why did you advise on an Intermediate Subcontract with subcontractors’ design (ICSub/D)?
- The terms of the Intermediate Subcontract offered parity with the main contract, which was an Intermediate Building Contract with the contractor’s design.
- The appointed sub-contractor had design responsibility.
- The subcontract allowed for adjustments in the form of variations.
Why did you go against your director’s advice when issuing a contract on the Caerphilly Ffos market?
- The subcontractors’ tender was so commercially advantageous compared to second place that it made sense commercially for LS to deviate from our standard terms to secure the Subcontractor’s use.
- The cost/risk-benefit of using a standard form sub-contract was a reasoned decision.
What was so contentious in Lancer Scott’s Terms and conditions that the subcontractor wasn’t willing to inherit?
The terms were issued with the tender pack, but the tender response from the Subcontractor was offered on the basis of their standard terms, which LS could not accept; as such, the subcontractor’s offer rejected Lancer Scott’s terms at the time of tender.
Was there anything in particular they contended against or was it the entire document?
The subcontractor had taken legal advice and opted not to agree to the document in its entirety.
So why would Lancer Scott opt to use their standard terms and conditions as opposed to using a subcontract if that option existed anyway?
The bespoke form has been drafted to favour Lancer Scott’s commercial interests and is the standard template for use on projects.
Why do you think bespoke forms of contract shouldn’t be used?
Non-standard bespoke contracts create many legal issues throughout drafting, review and negotiation. They are costly and time-consuming to produce and are untested in court.
What advantages do standard forms offer?
They are cost-effective, tested in court and drafted by clients, consultants and contractors alike. They are also updated based on case law.
What underpinned your advice about recommending an advanced payment bond?
- An advance payment would improve cash flow, allowing materials to be purchased.
- A bond would give the client security if Lancer Scott did not fulfil its obligations and protect against non-delivery of goods or services.
- The manufacturer would not offer credit terms due to the custom-cut ceramic stone made specifically for this project.
- The cost of the raw material specified by the client was high.
- I recommended an advance payment bond (APB) to reduce financial risk for both the employer and Lancer Scott.
- I also suggested early procurement of materials to secure a fabrication slot and ensure project timelines are met.
When did the bond expire?
The bond expired on the completion date outlined in the contract or repayment of the bond value.
How was the advanced payment repaid?
The advanced payment was repaid via deductions from Interim Payments.
What were the other options for repaying the bond?
- Repayment via Milestones.
- Lump Sum Repayment.
- Reduction from Final Payment.
- Set-off Against Future Payments.
What was the mechanism for this?
Adjusting the previously paid to include the value of material delivered to site.
Why did you go with deductions from interim payments?
Deductions from interim payments was a fair and reasonable option for maintaining cash flow and provided surety for the employer.
What would be the risk for Lancer Scott if the employer had called off against the bond.
It could damage credit rating or prevent lancer Scott from getting a bond in the future, or increase the cost of future bonds.
With that in mind why did you still recommend it?
- The material type was specified by the employer because we were governed by planning, it was a non-material amendment.
- The only way we could procure the material was through an advanced payment to the material manufacturer.
- An advanced payment would mean that Lancer Scott would not have to use its cash to do this.