3.3 Critical path analysis Flashcards

1
Q

Critical path analysis

A

A project management tool used for network analysis to plan the shortest amount of time to complete a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why do businesses need to plan complex projects?

A

Because it involves significant investment and risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What’s it necessary to do because complex projects involve significant investment and risk?

A

Necessary to identify relationships between activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does critical path analysis include?

A

List of all activities required to complete the project.
Time each activity will take to complete.
How each activity depends on each other.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does a critical path analysis show?

A

Longest part of project activities.
Earliest and latest activity stop times.
Critical project activities which if delayed will cause the project to run over.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does critical path analysis allow for?

A

Resources can be hired at the right time and quantity.
Working capital can be managed.
When delays occur managers can identify implications and redirect resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Node

A

Circle represents point in time where activity is started or finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Left of Node

A

Activity number

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Top of node

A

Earliest time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Bottom of node

A

Latest time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Activity

A

Process or project which takes time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is activity shown as?

A

Shown as a line which links nodes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Duration

A

Length of time it takes to complete a task.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What normally represents an activity?

A

Description or letter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Where is duration?

A

Number of hours or days below activity line.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Rules for critical path analysis

A

Always starts and ends on node.
Line must not cross.

17
Q

How to work out EST?

A

Adding duration of task.

18
Q

What direction do you work out EST?

A

Left to right

19
Q

When two activities meet what do u choose for EST?

A

Highest calculated figure.

20
Q

How to work out LST?

A

Subtracting the duration of each task.

21
Q

What direction do you work out LST?

A

Right to left

22
Q

When two activities meet what do u choose for LST?

A

Lowest calculated figure

23
Q

What does the critical path identify?

A

Activities that determine the length of the process.
Activities that will delay the project as a whole.
Nodes where EST and LST are equal.

24
Q

Float

A

duration an activity can be extended or delayed and the project will still finish in a minimum time.

25
Q

Formula for Float

A

LFT- Duration- EST

26
Q

Critical path

A

Activities with a float of 0 cannot be delayed without delaying the whole process.

27
Q

How can managers use float time?

A

To transfer resources
Allow extra time

28
Q

What’s the use of critical path analysis?

A

Estimate and minimise project time
Prioritise tasks
Plan and organise resources

29
Q

Limitations of critical path analysis

A

Very lengthy projects may have a large number of activities.
Network Analysis often relies on estimates and forecasts.
Network analysis does not guarantee success of project.

30
Q

What may be required for lengthy projects with a large number of activities?

A

Specialist network planning software

31
Q

What may be required for network analysis using estimates ?

A

Significant research

32
Q

What may be required for network analysis not guaranteeing success?

A

Highly skilled project managers.